首页 > > 详细

辅导NFO 4800 辅导asp

INFO 4800 
Midterm Exam (Summer 2020) 
 
Summer 2020 Page 1 
 
Instructions 
Place your name and student number at the top of the first page. Place the following statement under your name: “I have 
worked on this exam independently and have not given nor received help from anyone.” 
 
Format the answers as Times New Roman, 10 pt. Single Spaced, number all of the pages. Start each Chapter on a separate 
page by entering inserting a page break. Please write out each case question as a sub-heading, underline it and answer the 
question. Insert page number at the bottom right of each page. Leave a blank line between questions. Turn in exams prior to 
Tuesday, June 30, 11:59 pm in both a Word and PDF file using the file format: lastname-midterm.docx (also the MPP or 
GAN file). 
 
Questions 
E1: (a) Identify and discuss each of the project constraints. (b) Which one has traditionally been stable and what is the 
result of that? (c) Which one is now being held stable and what are the benefits of that? (5 pts) 
 
E2: (a) What are the nine (9) knowledge areas of project management? (b) Discuss each of the project management five (5) 
process groups. (5 pts) 
E3: (a) What are the five (5) methods for selecting projects? (b) Discuss each one in a sentence. (c) Which one is better? (5 
pts) 
E4: Draw a GANTT chart for the following activities. The project starts July 1, 2020. Be sure to show the % task 
completed and resources on the chart. Complete this problem in Microsoft Project or GanttProject and return the file with 
your Word and PDF files. (15 pts) 
 
Activity A is evaluating the technology platform and will take 2 days, is 100% complete and has John working 
100% on the task. Activity B is define user requirements and will take 5 days, is 90% complete and has John 
(50%), Sue (50%) working on the task, with predecessor A. Activity C – design web page layouts will take 4 
days, is 90% complete and has Kevin (75%), Marla (25%) working on the task with predecessor B. Activity D – 
set up server will take 3 days, is 75% complete with John (50%), Cristy (50%) working on the task with 
predecessor B. Activity E is estimate web traffic and will take 1 day, with predecessor B, is 75% complete with 
Jim (25%), Debbie (75%) working on the task. Activity F is test web pages will take 4 days, with predecessors C 
and D, is 0% complete with John (50%), Sue (50%) working on the task. 
 
Act Task Est 
Days 
Start 
Date 
End 
Date 
Pred. % Resources Percentage of 
Resources 
 
 
INFO 4800 
Midterm Exam (Summer 2020) 
 
Summer 2020 Page 2 
 
E5: Calculate the NPV, ROI, and Payback for the following problem (15 pts): 
 
E6: (a) There are different ways to estimate project tasks. (b) Identify each of the project estimation techniques and give a 
definition of each. (c) What happens when we constantly underestimate project tasks? (5 pts) 
 
E7: (a) Calculate the expected duration for the following tasks. (b) Draw the CPM Chart using the critical path method. (c) 
Identify all of the paths and select the critical path. (d) How much total slack do we have in the system? (15 pts) 
 
Act 
 
Predecessor 
Optimistic 
Estimate 
Most Likely 
Estimate 
Pessimistic 
Estimate 
Expected 
Duration 
A 1 2 4 
B A 3 5 8 
C B 2 4 5 
D B 2 3 6 
E B 1 1 1 
F C,D 2 4 6 
G D,E 2 3 4 
H F,G 1 2 5 
I G 4 5 9 
J HI .5 1 3 
 
 
E8: (a) Project scheduling involves 7 steps. Identify each of the 7 steps. (b) Indicate which two steps are the most critical 
and explain why. (10 pts) 
 
 
E9: (a) What are the steps to enter work resource pay rates in Microsoft Project? (b) What are the steps to adjusting 
working time in a resource calendar? (c) How does Microsoft Project calculate “work”? 
 
 
 
 
Discount rate 7% 
Year 
1 2 3 4 
Costs 300,000 40,000 40,000 40,000 
Discount factor 0.93 0.87 0.82 0.76 
Discounted costs 279,000 34,800 32,800 30,400 
Benefits 0 120,000 120,000 120,000 
Discount factor 0.93 0.87 0.82 0.76 
Discounted benefits 0 104,400 98,400 91,200 
Cumulative benefits 279,000 313,800 346,600 377,000 
Cumulative costs 0 104,400 202,800 294,000 
NPV 
ROI 
PB 
联系我们
  • QQ:99515681
  • 邮箱:99515681@qq.com
  • 工作时间:8:00-21:00
  • 微信:codinghelp
热点标签

联系我们 - QQ: 99515681 微信:codinghelp
程序辅导网!